EDINBURGH STAGE 6 INDUSTRIAL SUB-DIVISION
Elizabeth, South Australia
CLIENT
Land Management Corportation (LMC)
PROJECT SCOPE
Civil and Infrastructure Works
PROJECT SUMMARY
Project Summary
Site clearing.
Installation of Stormwater Infrastructure.
Bulk earthworks.
Level 1 Supervision.
Removal of redundant Services.
Asbestos removal.
CONSTRUCTION SUMMARY
- The 60,000m2 industrial subdivision released by Land Management Corporation (LMC) required preparation works including, site clearing (tree removal and grubbing), bulk earthworks build up to Level 1 Supervision, stormwater infrastructure and the removal of redundant services.
The placement and compaction of 21,000m3 of fill to Level 1 Supervision was undertaken with the use of GPS machine controlled graders. The whole site was finished within the construction tolerance of +/-10mm of the design levels for the entire site - as verified by an independant 'As Built' survey.