top of page

FEDEX

Netley, South Australia

bg-object2_edited.png

CLIENT

Dzine Construction Group

PROJECT SCOPE

Bulk Earthworks, Kerb, Concrete (Light & Heavy Duty) and Bitumen Pavement   

PROJECT SUMMARY

Australasian Construction was awarded the subcontract by Dzine Construction Group for the completion of civil works adjacent to Adelaide Airport for the new facility (~64,000 sqm) which is part of the planned freight and logistics hub for Adelaide Airport East Precinct. The scope of work for the project consisted of bulk earthworks, heavy-duty concrete pavement (~21,000 sqm) & light-duty bitumen car park (~10,000 sqm). Our specialized range of in-house machinery was used to meet the Client's needs for sub-grade and pavement layers to be filled and trimmed to various design RLs and within +/-10 mm tolerance. All works were inclusive of fill under Level 1 Supervision and pavement rubble.

CONSTRUCTION SUMMARY

    • Amend site won material for reuse, inclusive of removal of oversized and unsuitable material (with use of in-house specialized plant).

    • Cut to fill of sub-grade to design RLs.

    • Place, compact and final trim of pavement rubble across the site to design RLs.

    • Compaction of all layers achieved with the use of pad foot & smooth drum vibrating roller.

    • Sub-grade final trim for building pad ~24,000 sqm achieved by specialized machinery with inbuilt GPS and laser-capable positioning systems.

    • Trimming to appropriate levels to accommodate for bitumen, heavy-duty concrete, & building pad across the site.

    • Undertook sub-base, bitumen, kerb, gutter & line marking works to supply functional car parking facilities.

bottom of page